Construction Proposal Example — Warehouse Mezzanine & Office Fit-out

Example document for Construction Proposal. Use this as a reference when creating your own.

Professional Review Recommended

This document may have legal or financial implications. We recommend having a qualified professional review the final version before use.

Document: Construction Proposal

Example Document

Last updated 6/4/2026

Construction Proposal — Warehouse Mezzanine & Office Fit-out

Project: Mezzanine floor + ground-floor office fit-out Site address: 14 Foundry Way, Eastvale Industrial Estate Prepared for: Apex Distribution Pty Ltd (Site Manager: Dean Whitfield) Prepared by: Granite Ridge Construction (Licence no. BC-48217) Date: 4 June 2026 Valid until: 4 July 2026


1. Project overview

Apex Distribution needs additional usable floor area without leaving its current warehouse. Granite Ridge Construction proposes to build a 240 m² structural-steel mezzanine over the existing pick-and-pack zone and to fit out a 95 m² ground-floor office beneath it — meeting rooms, open workstations, and amenities — inside the existing building envelope. The contract sum is $318,500 + GST, with practical completion targeted for early September 2026.

2. Scope of work

  • Site & preparation — protect existing racking and stock, set out mezzanine grid, core-drill for column base plates, establish temporary site fencing within the warehouse.
  • Structure — supply and erect a galvanised structural-steel mezzanine (240 m²) with a 19 mm structural particleboard deck, edge protection balustrade, and a 1.2 m-wide compliant staircase with landing.
  • Office fit-out — steel-stud and plasterboard partitions forming two meeting rooms, an open work area, a kitchenette, and an accessible WC; suspended ceiling with LED panel lighting.
  • Services — electrical sub-board, power and data to all workstations, mechanical ventilation and split systems to the office, plumbing rough-in and fit-off for the kitchenette and WC.
  • Finishes — commercial vinyl plank flooring to the office, paint to all new walls, glazed partition to the larger meeting room, signage to the staircase.
  • Completion — builder's clean, mechanical and electrical commissioning, and a handover pack with certificates, warranties, and as-built drawings.

3. Materials & specifications

ElementSpecificationSupply by
Mezzanine frameHot-dip galvanised structural steel, engineer-certified to AS 4100Builder
Decking19 mm structural flooring-grade particleboard, screw-fixedBuilder
Partitions92 mm steel stud, 13 mm plasterboard both faces, insulatedBuilder
Office flooringCommercial-grade luxury vinyl plank, 4 mmBuilder (allowance)
Lighting600x600 recessed LED panels, 4000KBuilder
Split systems2 x 7.1 kW inverter units, office zonesBuilder
Kitchenette joineryLaminate cabinetry, client to select finishBuilder (allowance)

4. Schedule & phases

PhaseWorksDurationMilestone
1Site set-out, base plates, protection1 weekSet-out signed off
2Steel erection, decking, balustrade, stairs3 weeksMezzanine structurally complete
3Office framing, services rough-in, ceilings3.5 weeksLock-up of office
4Finishes, mechanical fit-off, commissioning2.5 weeksPractical completion

Estimated start: 14 July 2026 Estimated completion: 5 September 2026 Schedule assumes warehouse operations continue alongside works and that the pick-and-pack zone is cleared by Apex before Phase 1.

5. Pricing

Pricing model: Fixed price (lump sum)

ItemDetailAmount
Site preparationProtection, set-out, base plates$18,400
Mezzanine structureSteel, deck, balustrade, staircase$146,800
Office fit-outPartitions, ceilings, finishes$72,300
ServicesElectrical, mechanical, plumbing, data$68,000
Completion & handoverClean, commissioning, documentation$13,000
Subtotal$318,500
GST (10%)$31,850
Contract sum$350,350

6. Payment schedule / milestones

StageTrigger% of contractAmount (inc. GST)
DepositOn acceptance10%$35,035
Progress 1Mezzanine structurally complete35%$122,623
Progress 2Office locked up30%$105,105
Progress 3Services commissioned15%$52,553
FinalPractical completion + handover10%$35,034

Progress claims are issued on milestone completion and are due within 14 days. A 5% retention on each progress payment is held and released 90 days after practical completion.

7. Allowances & exclusions

Allowances (provisional sums):

  • Office flooring (luxury vinyl plank) — $9,500 allowance; adjusted on final product selection.
  • Kitchenette joinery and benchtop — $6,000 allowance; adjusted on final finish selection.

Exclusions:

  • Removal of existing racking or relocation of stock (by Apex).
  • Fire-services upgrades or sprinkler relocation, if required by the certifier.
  • Any rectification of pre-existing slab cracking or hazardous materials discovered during core-drilling.
  • Loose furniture, IT hardware, and network cabling beyond the data outlets specified.

8. Permits & compliance

Granite Ridge Construction will lodge and manage the building permit. The mezzanine is engineer-designed and certified to AS 4100 (steel structures) with footing certification to the relevant slab assessment. All electrical work is carried out by a licensed electrician with a certificate of compliance on completion, and plumbing carries a compliance certificate. The accessible WC is built to the applicable access standard. A final occupancy inspection is included before handover.

9. Warranty

Workmanship is guaranteed for 24 months from practical completion. Manufacturer warranties on supplied products (steel coatings, split systems, flooring) are passed through to Apex in the handover pack. Defects reported in writing during the warranty period will be assessed within 5 business days and rectified at no cost where attributable to Granite Ridge workmanship.

10. Terms & assumptions

  • Working hours: weekdays 6:30am–3:30pm; out-of-hours work by prior agreement.
  • Apex provides site power, water, and a designated waste and skip area.
  • Variations to scope are priced and approved in writing before the affected work proceeds.
  • This proposal is valid until 4 July 2026; steel and material prices are subject to confirmation after that date.

11. Acceptance

By signing below, Apex Distribution accepts the scope, specifications, schedule, and pricing above.

Accepted by: ______________________ Date: ____________ On behalf of Granite Ridge Construction: ______________________

Notes

A realistic worked example for a steel mezzanine and office fit-out; all dimensions, specifications, and dollar figures are illustrative.

About this Example

Part of the Construction Proposal document collection

Document Type

Construction Proposal

A detailed proposal for a construction project covering scope, materials, timeline, costs, and compliance.

Complexity

complex

Risk Level

medium