Implementation Plan Example — ERP Rollout

Example document for Implementation Plan. Use this as a reference when creating your own.

Professional Review Recommended

This document may have legal or financial implications. We recommend having a qualified professional review the final version before use.

Document: Implementation Plan

Example Document

Last updated 6/4/2026

Implementation Plan — ERP Rollout at Northwind Manufacturing

Project / initiative: Replace legacy accounting and inventory systems with a unified ERP Sponsor: Priya Desai, CFO Delivery lead: Tom Akande, IT Programme Manager Date: 4 June 2026 Version: v1.0 Status: Approved


1. Objectives & scope

Objectives:

  • Retire the three disconnected legacy systems and run finance, inventory, and purchasing on one ERP by Q4 2026.
  • Cut month-end close from 9 working days to 4.
  • Give all 6 branch warehouses real-time, shared stock visibility (currently updated overnight in batches).

In scope: Finance (GL, AP, AR), inventory, and purchasing modules across head office and 6 warehouses.

Out of scope: The shop-floor MES, HR/payroll, and the customer-facing webstore — these stay on their current systems and integrate via the existing middleware. CRM migration is a separate, later project.

2. Phases & milestones

PhaseGoalKey milestoneTarget date
1Discovery & designRequirements and to-be process maps signed off31 Jul 2026
2Configure & buildERP configured and passing UAT in staging18 Sep 2026
3Data migration & pilotHead office live on ERP, stable for 2 weeks16 Oct 2026
4Warehouse rolloutAll 6 warehouses migrated and transacting27 Nov 2026
5Stabilise & handoverSupport handed to internal BAU team, legacy systems off18 Dec 2026

3. Workstreams & owners

WorkstreamScope of the trackAccountable owner
ERP configurationModule setup, workflows, integrationsTom Akande
Data migrationCleanse and migrate master data + open balancesLena Ortiz (Finance Systems)
Training & changeTrain 140 staff across head office + warehousesSam Okoro (Ops)
CommunicationsStakeholder updates, branch readinessTom Akande

4. Resource plan & RACI

Resources required:

  • People: 2 IT staff full-time, a finance SME at 50%, and the ERP vendor's 2-person delivery team for Phases 1 to 3.
  • Budget: 240,000 USD (licences, vendor services, 3 months of contingency support).
  • Tools / systems: ERP staging and production tenants; the existing middleware for the MES integration.

RACI:

Activity / decisionCFO (Sponsor)Delivery leadWorkstream ownerBranch managers
Approve to-be processesACRC
Configure & test ERPIARI
Sign off data migrationARRI
Go/no-go for each warehouseARCC

5. Timeline

MilestonePhaseOwnerDate
Requirements signed off1Tom Akande31 Jul 2026
UAT passed in staging2Tom Akande18 Sep 2026
Head office live (pilot)3Lena Ortiz2 Oct 2026
All warehouses migrated4Sam Okoro27 Nov 2026
Legacy systems decommissioned5Tom Akande18 Dec 2026

The critical path runs through data migration: clean master data must be ready before any cutover, so a two-week buffer sits between UAT and the head-office go-live to absorb cleansing overruns.

6. Dependencies

DependencyNeeded beforeOwnerStatus
Master data cleansed (suppliers, items)Phase 3 migrationLena OrtizOpen
Middleware mapping for MES integrationPhase 2 buildIT vendorOpen
Warehouse network upgrade (Branch 4)Phase 4 rolloutFacilitiesDone

7. Risks & mitigations

RiskLikelihoodImpactMitigation / triggerOwner
Dirty legacy data delays migrationMHStart cleansing in Phase 1; weekly data-quality report; pad critical path with 2 weeksLena Ortiz
Branch staff resist the new systemMMTrain per branch a week before its go-live; on-site support for first 3 daysSam Okoro
Month-end falls during a cutoverLHSchedule every warehouse go-live for the first week of a month, never near closeTom Akande

8. Communication plan

AudienceWhat they needFrequencyChannelOwner
CFO & exec teamStatus, risks, decisions neededWeeklySteering meetingTom Akande
Branch managersTheir go-live date and readiness checklistAt each phase + 1 week before go-liveEmail + callSam Okoro
All affected staffWhat changes for them and whenAt Phase 3 and Phase 4Briefing + intranetSam Okoro

9. Success measures

  • All transactions running on the single ERP, with the three legacy systems switched off by 18 Dec 2026 (maps to Objective 1).
  • Month-end close completed in 4 working days or fewer for two consecutive months post go-live (maps to Objective 2).
  • Stock levels visible in real time across all 6 warehouses, confirmed by a spot-check reconciliation (maps to Objective 3).

Notes

A filled implementation plan for a fictional ERP rollout, showing phases, workstreams, dependencies, and risks; names, dates, and figures are illustrative.

About this Example

Part of the Implementation Plan document collection

Document Type

Implementation Plan

A detailed plan for implementing a project, system, or initiative, including phases, tasks, resources, and timelines.

Complexity

complex

Risk Level

medium