Project QA Plan Example — Website Build Project
Example document for Project QA Plan. Use this as a reference when creating your own.
For Informational Purposes
This document template is provided for informational purposes. Customize it for your specific needs.
Document: Project QA Plan
Example Document
Last updated 6/4/2026
Project QA Plan — Riverbend Cafe Website Build
Project: Riverbend Cafe marketing website (build and launch) Sponsor / client: Riverbend Cafe (owner: M. Alvarez) Author: T. Okafor, Delivery Lead Date: 5 June 2026 Reviewers: S. Hughes (Design), R. Patel (Client liaison) Status: Approved
1. Project and scope
This project delivers a five-page marketing website for Riverbend Cafe — home, menu, about, events, and contact — plus a content-managed blog. This QA plan covers all design, content, build, and accessibility deliverables. Hosting platform uptime is out of scope, as it is covered by the host's own service agreement.
2. Quality objectives and acceptance criteria
| Deliverable | Acceptance criteria (specific, checkable) | Standard / reference | Accepted by |
|---|---|---|---|
| Visual design (Figma) | Matches approved brand palette and type scale; covers all 5 page types and mobile + desktop | Riverbend brand guide v2 | Client (M. Alvarez) |
| Page content | No spelling errors; every menu price matches the supplied price list; contact details correct | Supplied copy deck | Client liaison (R. Patel) |
| Built pages | Pixel match to design within tolerance; works in Chrome, Safari, Firefox; no console errors | Design (Figma) | Delivery Lead |
| Accessibility | All pages pass automated checks at WCAG 2.1 AA; keyboard navigable; images have alt text | WCAG 2.1 AA | Design reviewer |
| Performance | Home page Largest Contentful Paint under 2.5s on a mid-range mobile profile | Web vitals target | Delivery Lead |
3. Review and approval gates
| Gate | Applies to | Entry condition | Exit condition (passed when) | Decider |
|---|---|---|---|---|
| Author self-check | All | Draft complete | Self-check checklist passed | Author |
| Peer review | Design, content, build | Self-check passed | Comments resolved; criteria met | S. Hughes / T. Okafor |
| Accessibility review | Built pages | Build peer review passed | WCAG 2.1 AA checks pass | S. Hughes |
| Client sign-off | Design, content, final site | Internal gates passed | Client accepts by email | M. Alvarez |
4. Roles and responsibilities (RACI)
| Activity | Responsible (R) | Accountable (A) | Consulted (C) | Informed (I) |
|---|---|---|---|---|
| Maintain this QA plan | T. Okafor | T. Okafor | S. Hughes | Team |
| Review design deliverables | S. Hughes | T. Okafor | R. Patel | M. Alvarez |
| Review content | R. Patel | T. Okafor | M. Alvarez | S. Hughes |
| Accessibility review | S. Hughes | S. Hughes | T. Okafor | Team |
| Client sign-off | R. Patel | M. Alvarez | T. Okafor | Team |
| Triage and track defects | T. Okafor | T. Okafor | S. Hughes | Team |
5. Defect / issue process
- Raising an issue: Logged in the shared issue tracker with a screenshot, the page, and steps to reproduce.
- Severity scale:
- Critical — broken page, wrong price, or blocked checkout/contact path.
- Major — feature works incorrectly with no clean workaround.
- Minor — cosmetic spacing, copy nit, or low-impact visual difference.
- Triage: T. Okafor reviews new issues each weekday morning and assigns severity and owner.
- Resolution rule at sign-off: No open Critical or Major defects at client sign-off; agreed Minor issues move to a launch-week backlog recorded in the tracker.
- Tracking: All issues live in the tracker; closure requires the reviewer to confirm the fix.
6. Quality metrics
| Metric | How measured | Target / threshold | Owner |
|---|---|---|---|
| Open defects by severity | Count from tracker | 0 Critical / 0 Major at sign-off | T. Okafor |
| First-time review pass rate | Deliverables passed / reviewed | At least 75% | S. Hughes |
| Post-launch escapes | Issues raised in week 1 after launch | Fewer than 3 | T. Okafor |
7. Audit / review schedule
| Activity | When / frequency | Performed by | Output |
|---|---|---|---|
| Design QA checkpoint | End of design phase | S. Hughes | Findings + actions |
| Pre-launch accessibility audit | Before client sign-off | S. Hughes | Audit note |
| QA plan review | Start of each phase | T. Okafor | Updated plan |
Notes
A realistic worked example showing per-deliverable acceptance criteria, review and approval gates, a RACI matrix, and a defect process for a small website build. Names, dates, and thresholds are illustrative.