Asbestos Removal Control Plan Example
Example document for Asbestos Removal Control Plan. Use this as a reference when creating your own.
Professional Review Required
This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.
Document: Asbestos Removal Control Plan
Example Document
Last updated 7/29/2026
Asbestos Removal Control Plan
Project Details:
- Client/PCBU Name: Smithtown High School P&C
- Site Address: 12 Education Drive, Smithtown NSW 2000
- Date of Plan Preparation: 12 October 2023
- Supervisor Name: John Doe
- Licence Number: 123456B
- Licence Class: Class B
- Work Start Date: 15 October 2023
- Expected Work End Date: 16 October 2023
1. Asbestos Details
- Location of Asbestos: Exterior eaves of the Main Hall building.
- Type of Asbestos: Non-Friable (Bonded)
- Quantity/Square Metres: 25 square metres.
- Condition of Material: Weathered, surface cracking observed.
- Residue/Risk: Moderate risk of fibre release if disturbed by dry cutting.
2. Consultation
We consulted the following people to prepare this plan:
- Workers: Mike Ross, Sarah Jenkins
- Site Management: Janet Brown, School Principal
- Other PCBUs: None on site during weekend work.
3. Training and Information
All workers involved in this job have received:
- Asbestos Awareness Training
- Asbestos Removal Training (Class B)
- Site-specific induction
Training records are held at: Head Office, 44 Industrial Way.
4. Control Measures
Preparation
- Area isolated with barriers and tape
- Warning signs displayed (Danger Asbestos Removal Area, No Smoking)
- Electrical and gas services isolated (nailed to timber is low risk)
- HVAC systems sealed (window unit turned off)
Removal Method
- Technique: Wet Method. Plastic sheeting drop sheets laid below work area.
- Tools: Hand tools only. Scrapers and manual pliers. No power tools.
- Water Suppression: Garden spray pump with surfactant (wetting agent) used to soak sheets before and during removal.
Decontamination
- Location of Decon Unit: Portable decon shower set up at rear of building, near access point.
- Procedure: Workers enter dirty zone, remove boots, shower down, remove suits in shower, dry off, exit clean zone to change area.
5. Personal Protective Equipment (PPE)
All workers must wear:
- Disposable coveralls (Type 5, with hood and boot covers)
- Respirator (P3) - Fit tested yesterday
- Disposable nitrile gloves
- Safety boots (laceless gumboots)
6. Waste Management
- Waste Container Type: 200 micron red asbestos waste bags.
- Labelling: All bags labelled with Asbestos Warning sticker and site address.
- Transport: Transported in locked, lined trailer by Asbestos Safe Removals.
- Disposal Site: Cleanaway Special Waste Facility, Western Sydney.
7. Air Monitoring
- Is air monitoring required? Yes (clearance monitoring).
- If Yes, Hygienist Name: Dr David Green
- Hygienist Company: ABC Hygiene Services
- Type of Monitoring: Clearance and Visual Inspection.
8. Emergency Procedures
Fire: Evacuate to the far end of the oval and call 000. Use fire extinguisher (CO2) on electrical fires only if safe. Incident (Uncontrolled fibre release): Stop work immediately. Close windows. Sprinkle water on spill. Isolate zone. Call Supervisor. First Aid: Located in the School Administration building (50 metres away). Code to access is 1234.
9. Sign-off
I confirm that this control plan has been prepared following consultation. I will ensure that all workers understand and follow this plan.
Supervisor Signature: J Doe Date: 12/10/2023
We, the undersigned workers, have read and understood this Asbestos Removal Control Plan.
- M Ross
- S Jenkins
Notes
The example above shows a removal job for Non-Friable asbestos exceeding 10 square metres. It details wet methods, hand tools, and mandatory clearance air monitoring. The decontamination procedure is specific to a portable unit setup.
About this Example
Part of the Asbestos Removal Control Plan document collection
Document Type
Asbestos Removal Control Plan
A written document outlining the procedures for safely removing asbestos at a workplace to protect workers and the public.