Construction Method Statement Example
Example document for Construction Method Statement. Use this as a reference when creating your own.
Professional Review Required
This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.
Document: Construction Method Statement
Example Document
Last updated 7/30/2026
Project Details
Project Name: Smith Residence Deck Extension Project Address: 42 Builder Street, Richmond, VIC 3121 Client Name: John Smith Date Prepared: 12 October 2023 Prepared By: Quality Decks Pty Ltd
1. Project Description
Construction of a 40 square meter elevated timber deck at the rear of the existing dwelling. Works include removal of old paving, installation of timber posts, bearers, joists, and decking boards. Installation of glass balustrade and timber stairs. Value: $25,000.
2. Site Information
The site is a residential backyard with side access 1.5m wide. Access is restricted for large machinery. The ground slopes away from the house. Public footpath is adjacent to the front driveway.
3. Standards and Legislation
- Work Health and Safety Act 2011
- Work Health and Safety Regulation 2011
- AS 1684 Residential Timber Framing Code
- AS 1428 Design for Access and Mobility
4. Project Team and Responsibilities
- Project Manager: Bob Builder - Responsible for overall safety compliance.
- Site Supervisor: Steven Site - Responsible for daily safety monitoring.
- First Aid Officer: Steven Site - Responsible for first aid treatment.
5. Sequence of Works
- Site setup including fencing and signage.
- Marking out of post locations.
- Digging of 9 post holes (600mm diameter).
- Concreting of stirrups and posts.
- Installation of bearers and joists.
- Fixing of decking boards.
- Installation of glass balustrade.
- Construction of stairs.
- Site cleanup and handover.
6. Risk Management
| Task / Activity | Hazard | Risk Level | Control Measures |
|---|---|---|---|
| Manual Handling | Back injury | Medium | Use trolley for cement bags. Team lift for bearers. |
| Excavation | Underground services | High | Dial Before You Dig on site. Hand digging near services. |
| Working at Heights | Fall > 2m | High | Scaffold edge protection. Fall arrest harnesses. |
| Use of Power Tools | Electric shock / laceration | Medium | RCD testing. Tool box talk. PPE including glasses and gloves. |
7. Plant and Equipment
- Post hole digger - Current inspection tag valid
- Circular Saw - Current inspection tag valid
- Cordless Drill - Visual inspection passed
- Mobile Scaffold - Tagged and compliant
8. Environmental Management
- Dust: Light water spray during cutting.
- Noise: Restricted noisy work to 7am to 6pm weekdays. Notify neighbors prior.
- Waste: All timber offcuts collected in skip bin. Concrete waste disposed of at licensed facility.
9. Emergency Procedures
- Fire: Evacuate to assembly point at front nature strip. Call 000. Use fire extinguisher on small fires if safe to do so.
- First Aid: First aid kit located in site shed.
- Emergency Contact: 000
10. Sign Off
I acknowledge that I have read and understood this Construction Method Statement.
Workers Signature: S. Site Date: 12/10/2023
Principal Contractor Approval: B. Builder Date: 12/10/2023
Notes
This example highlights the need for specific detail. Note how the Risk Management table links specific hazards to specific controls. The Environmental section addresses potential neighborhood issues common in residential builds. The Sign Off section proves that workers have actually read the document.
About this Example
Part of the Construction Method Statement document collection
Document Type
Construction Method Statement
A document outlining how a construction project will be carried out safely, efficiently and in compliance with Australian regulations.