PropoDoc provides self-help document templates and tools. It is not a law firm and does not provide legal advice. Learn more.
Skip to main content
Example
form

Excavation Permit Example

Example document for Excavation Permit. Use this as a reference when creating your own.

Professional Review Required

This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.

Document: Excavation Permit

Example Document

Last updated 7/29/2026

EXCAVATION PERMIT

Permit Number: EP-2023-045 Site Address: 42 Smith Street, Parramatta NSW 2150 Project Name: Smith Street Apartment Block

1. WORK DETAILS

Description of Work: Excavation for stormwater pit installation near car park entrance. Location on Site: Front driveway, 2 metres south of the roller door. Start Date: 15/11/2023 Start Time: 07:00 AM Expected Finish Date: 15/11/2023

Maximum Depth of Excavation: 1.8 metres Volume of Material to be Removed: 4 cubic metres

2. MACHINERY AND EQUIPMENT

Plant/Equipment to be Used: 1.8 Tonne Mini Excavator (Bobcat E85), Hand Tools for finishing. Make and Model: Bobcat E85 Operator Name: John Smith Operator Licence Number: LIC-99887766

3. UNDERGROUND SERVICES (Dial Before You Dig)

BYDA Ref Number: BYDA-55667788 Date of Enquiry: 10/11/2023

Known Services in Area:

  • Electrical (Ausgrid)
  • Gas (Jemena)
  • Water (Sydney Water)
  • Telecommunications
  • Sewer
  • Stormwater
  • Other: N/A

Have plans been received? [X] YES [ ] NO Have assets been potholed/located on site? [X] YES [ ] NO Have assets been clearly marked? [X] YES [ ] NO Note: Gas main potholed and found 200mm deeper than plan. Water main located with scanner.

4. RISK ASSESSMENT AND CONTROLS

Soil Type: Stable Clay Ground Water Level: NONE

Is ground support required? [X] YES [ ] NO If YES, specify type (shoring, benching, shielding): Trench Shields used for depths over 1.5m.

Hazard Identification:

  • Traffic movement (car park access)
  • Underground services
  • Public access (Site fenced)
  • Falling objects
  • Noise
  • Dust

Control Measures:

  • Traffic controller used to manage cars entering driveway.
  • Exclusion zone of 1.5m around gas main maintained.
  • Trench shields installed before personnel entry.
  • Barriers and warning tape erected around perimeter.

5. SAFE WORK METHOD STATEMENT

SWMS Reference Number: SWMS-EXCAV-01 Is the SWMS available on site? [X] YES [ ] NO

6. AUTHORIZATION AND SIGN OFF

I confirm that:

  1. I have read and understood the requirements of this permit.
  2. The SWMS has been reviewed and controls are in place.
  3. All underground services have been identified and protected.
  4. The excavation area is clear of unnecessary personnel.
  5. I am authorised to carry out this work.

Authorised Person (Site Supervisor): Name: Sarah Jones Signature: S. Jones Date: 15/11/2023 Time: 06:45

Person Conducting Excavation (Permit Holder): Name: John Smith Signature: J. Smith Date: 15/11/2023 Time: 06:50

7. PERMIT CLOSURE

Work Completed: [X] YES [ ] NO Area Made Safe: [X] YES [ ] NO Excavation Backfilled: [ ] YES [X] NA (Pit installation requires open trench)

Signed Off By: Sarah Jones Signature: S. Jones Date: 15/11/2023

Notes

Key Decisions:

  • Ground Support: Since the trench was 1.8m deep, trench shields were mandatory to prevent collapse, even though the soil was clay.
  • Services: The potholing step was critical here because the Gas main was deeper than shown on the plans, preventing a potential strike.
  • Traffic: A traffic controller was required because the excavation blocked the usual driveway path, creating a collision risk.

About this Example

Part of the Excavation Permit document collection

Document Type

Excavation Permit

An official document allowing authorised digging or ground penetration. It ensures tradespeople identify and protect underground assets before work starts.

Complexity

moderate

Risk Level

high