PropoDoc provides self-help document templates and tools. It is not a law firm and does not provide legal advice. Learn more.
Skip to main content
Example
form

Extension of Time Claim Example

Example document for Extension of Time Claim. Use this as a reference when creating your own.

Professional Review Required

This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.

Document: Extension of Time Claim

Example Document

Last updated 7/29/2026

EXTENSION OF TIME CLAIM

Date: 15/08/2023

From: Superior Constructions Pty Ltd ABN: 12 345 678 901 123 Builder Street Sydney NSW 2000

To: Main Developments Ltd Attn: John Smith, Superintendent 456 Developer Avenue Sydney NSW 2000

Project Details: Project Name: Westfield Commercial Suite Fitout Project Address: Level 2, 500 George Street, Sydney Contract Number: MC-2023-88 Original Date for Practical Completion: 30/09/2023

Reference: This claim is made pursuant to Clause 4.12 of the AS 4000-1997 Contract.

Details of Qualifying Cause: We hereby give notice of a delay to the progress of the Works caused by Inclement Weather and Late Issue of Architectural Drawings.

Description of Event:

  1. Inclement Weather: Severe rainstorms occurred on the 1st, 2nd, and 3rd of August 2023. This prevented external glazing works and the delivery of materials to the site dock.
  2. Late Drawings: Structural detail drawings for the feature staircase (Drawing A-02 Rev C) were issued on 10/08/2023. This was 10 days later than the program date required to maintain the critical path.

Effect on Progress: Due to the rain, the external site hoarding was unsafe for delivery vehicles. The staircase steel fabrication could not commence until the drawings were verified.

Period of Delay:

DateWork AffectedReason for StoppageHours Lost
01/08/2023External GlazingHeavy rain / Site access unsafe8
02/08/2023Concrete PourRain8
03/08/2023Material DeliveryWet site conditions8
04/08/2023 to 14/08/2023Staircase FabricationWaiting for Structural Drawings80 (10 days)

Total Extension Claimed: We claim an extension of time of 13 calendar days.

Revised Date for Practical Completion: Based on this claim, the Date for Practical Completion should be adjusted to 13/10/2023.

Supporting Documents: Evidence attached to support this claim includes:

  • Site Diary
  • Bureau of Meteorology Rain Records (Sydney Observatory Hill)
  • Email confirming receipt of drawings on 10/08/2023
  • Original Program showing drawing due date

Request for Determination: We request that you grant this Extension of Time in accordance with the contract conditions. Please confirm acceptance of this claim and the revised Date for Practical Completion in writing within 7 days.

Yours faithfully,


Bill Jones Project Manager Superior Constructions Pty Ltd

Notes

Annotations:

  1. Contract Reference: The example cites Clause 4.12 of AS 4000. You must check your specific contract to find the correct clause number for delays.
  2. Separation of Causes: The claim splits the delay into two distinct parts: Weather and Drawings. This makes it harder for the superintendent to reject the whole claim if one part is disputed.
  3. Specific Dates: The example uses exact dates rather than vague terms like 'last week'. This precision is required for legal validity.
  4. Supporting Evidence: The list of attachments proves the claims. Rain records and emails are .
  5. Revised Date: The calculation simply adds the days to the existing date. Ensure you account for weekends or contract-specific definitions of 'working days'. AS 4000 usually uses calendar days unless specified otherwise.

About this Example

Part of the Extension of Time Claim document collection

Document Type

Extension of Time Claim

A formal request to a principal or head contractor for more time to complete construction work due to delays outside your control.

Complexity

moderate

Risk Level

high