Job Costing Sheet Example

Example document for Job Costing Sheet. Use this as a reference when creating your own.

Professional Review Recommended

This document may have legal or financial implications. We recommend having a qualified professional review the final version before use.

Document: Job Costing Sheet

Example Document

Last updated 7/30/2026

Job Costing Sheet

Business Name: Smith & Sons Plumbing Pty Ltd ABN: 12 345 678 901

1. Job Details

FieldDetails
Job Number / ReferenceJOB-2023-045
Client NameMrs. Joan Miller
Client Address42 Wallaby Way, Sydney NSW
Client Phone0412 345 678
Date Quote Sent10/10/2023
Job Start Date15/10/2023
Estimated Finish Date20/10/2023

2. Financial Summary

FieldAmount
Total Quote Price (Excl. GST)$4,500.00
Total Actual Cost (Excl. GST)$4,120.00
Actual Profit / Loss$380.00
Profit Margin8.4%

3. Labour Costs

Role / NameEst HoursHourly RateEst Labour CostAct HoursAct RateAct Labour CostDifference
J. Smith (Plumber)20$80.00$1,600.0022$80.00$1,760.00-$160.00
A. Apprentice20$35.00$700.0018$35.00$630.00$70.00
Total Labour$2,300.00$2,390.00-$90.00

4. Material Costs

Item DescriptionSupplierEst QtyEst Unit CostEst TotalAct QtyAct Unit CostAct TotalDifference
Copper Pipe (Type B)Reece30$25.00$750.0032$28.00$896.00-$146.00
Basin SetTradelink1$200.00$200.001$180.00$180.00$20.00
Solder & FluxBunnings1$50.00$50.001$45.00$45.00$5.00
Total Materials$1,000.00$1,121.00-$121.00

5. Subcontractors & Plant Hire

DescriptionSupplierEst CostAct CostDifference
Electrician (Point Repair)Sparky Co$400.00$400.00$0.00
Total Subcontracts/Hire$400.00$400.00$0.00

6. Other Expenses

Item DescriptionEst CostAct CostDifference
Council Inspection$100.00$100.00$0.00
Van Fuel (Est 3 trips)$100.00$109.00-$9.00
Total Other$200.00$209.00-$9.00

7. Notes & Variations

  • Copper pipe price increased unexpectedly at supplier. Added 2 meters due to waste.
  • Job finished 1 day late due to waiting on electrician.

Notes

This example shows a job that made a profit but less than expected. The labour cost increased because the plumber worked 2 extra hours. The material cost blew out because copper prices rose and more was needed for waste. This data helps the plumber quote higher for the next copper job.

About this Example

Part of the Job Costing Sheet document collection

Document Type

Job Costing Sheet

A record of all estimated and actual costs for a specific project or job, used by Australian tradespeople and businesses to track profitability and ensure pricing covers expenses.

Complexity

moderate

Risk Level

medium