Example document for SWMS - Masonry Worker (General). Use this as a reference when creating your own.

Professional Review Required

This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.

Document: SWMS - Masonry Worker (General)

Example Document

Last updated 7/30/2026

SAFE WORK METHOD STATEMENT (SWMS)

Company / Project Details

Company Name: BuildRight Constructions Pty Ltd ABN: 12 345 678 901 Project Address: 45 Smith Street, Parramatta NSW Date of Preparation: 12/10/2023 Work Activity: Bricklaying - External Walls & BBQ Area

Step 1: Describe the High Risk Construction Work

High Risk Construction Work ChecklistYes/No
Work involving a risk of a person falling more than 2 metresYES
Work carried out on or near pressurised gas distribution mains or pipingNO
Work carried out on or near chemical, fuel or refrigerant linesNO
Work on or near energised electrical installationsNO
Work involving mobile plantYES
Work in or near a confined spaceNO
Work in or near a shaft or trench deeper than 1.5 metresNO
Work involving demolitionNO
Work involving asbestosNO
Work in an area that may have a contaminated or flammable atmosphereNO
Work involving tilt-up or precast concreteNO
Work in an area with movement of powered mobile plantYES
Work on a telecommunications towerNO
Work near trafficNO

Description of Work: Construction of external brick veneer walls for new dwelling and construction of a raised brick BBQ. Work includes scaffolding setup, mortar mixing, brick cutting, and laying bricks at heights up to 4 metres using a telescopic handler.

Step 2: Hazard Identification

Step/TaskWhat is the Hazard?How could it cause harm?Risk RatingInitial Controls
1. Loading Bricks via TelehandlerMoving machinery, falling loadsCrushingHDedicated spotters, exclusion zone (3m), operator ticket, green tag
2. Manual Handling (Bundles)Heavy liftingBack strainMUse brick carts, lift in pairs, store at waist height
3. Work on ScaffoldingFall from height (4m)Death/Spinal injuryHFull scaffold (tagged), guardrails, access ladder, MW induction
4. Cutting Bricks with Drop SawSilica dust, noiseSilicosis, hearing lossHWet cutting on bench, P2 mask, ear muffs, wash down area
5. Falling ObjectsLoose bricks/toolsHead injuryHToe boards on scaffold, no throwing bricks, clean walkways
6. Lime/Mortar MixingCement burnDermatitisMLong sleeves, gloves, face shield, wash hands immediately
7. Working in HeatUV exposure, dehydrationSunstroke, fatigueMStart at 6am, 10min break per hour, provide water station

Step 3: Implementation of Control Measures

Key Task: Brick Cutting on Scaffolding

  • Elimination: Not possible for this task.
  • Substitution: Pre-cut bricks at ground level where possible to reduce height work.
  • Isolation: Use a small wet-cut saw on the scaffold bay, ensure tarp is below to catch slurry.
  • Engineering: Wet-cutting attachment connected to water supply. Use of RCD for saw power.
  • Administrative: Only cut essential bricks. Clean slurry immediately (wet method).
  • PPE: P2 respirator, safety glasses, ear muffs, nitrile gloves.

Key Task: Loading Materials

  • Elimination: Delivery direct to scaffold by contractor.
  • Engineering: Use of telescopic handler with brick grab.
  • Administrative: Pedestrian exclusion zone enforced. Traffic controller present.
  • PPE: High vis, steel caps, helmet.

Step 4: Personal Protective Equipment (PPE)

Minimum PPE:

  • High visibility shirt (orange)
  • Safety helmet (white)
  • Safety boots (elastic sided)
  • Safety glasses
  • Broad brim hat
  • Sunscreen (SPF 50+)

Task Specific:

  • P2 Respirator (cutting)
  • Ear muffs (cutting)
  • Heavy duty gloves (handling)
  • Long sleeve shirt (mixing/cutting)

Step 5: Emergency Procedures

Incident Reporting: Contact Site Foreman, John Smith, on 0400 123 456.

First Aid: Kit located in site office near amenities. Nearest Hospital: Westmead Hospital, Hawkesbury Rd, Westmead.

Fire: Call 000. Meeting point at the front gate (Smith Street).

Step 6: Review and Monitoring

Review Triggers:

  • If weather becomes wet and slippery (scaffolding risk).
  • If new machinery brought to site.

Review Date: 25/10/2023

Signatures

NameRoleSignatureDate
John SmithWorker RepJ.Smith12/10/23
Mary JonesPCBUM.Jones12/10/23
Steve RogersWorkerS.Rogers12/10/23
Tony StarkWorkerT.Stark12/10/23

Notes

Annotations: This example shows a practical application for a typical residential build. Note the inclusion of 'Wet cutting' as the primary control for silica dust, which is mandatory. The exclusion zones for the telehandler are clearly defined. The risk rating reflects the reality of working at height.

About this Example

Part of the SWMS - Masonry Worker (General) document collection

Document Type

SWMS - Masonry Worker (General)

Use this SWMS for general bricklaying, blockwork, and stone masonry tasks on construction sites. It covers high-risk work like working at heights, manual handling, and using powered tools.

Complexity

complex

Risk Level

high