SWMS - Roadworks / Civil Construction Example

Example document for SWMS - Roadworks / Civil Construction. Use this as a reference when creating your own.

Professional Review Required

This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.

Document: SWMS - Roadworks / Civil Construction

Example Document

Last updated 7/30/2026

Safe Work Method Statement (SWMS)

Company Details

Company Name: Apex Civil Contractors Pty Ltd ABN: 12 345 678 901

Project / Job Details

Project Name: Main Street Utility Upgrade Site Address: 100 Main Street, Brisbane QLD Date of Issue: 15 October 2023

High Risk Construction Work (HRCW)

  • Excavation work (deeper than 1.5m)
  • Work near traffic, mobile plant
  • Work near energised electrical installations

Description of Tasks

  1. Establish Traffic Control Devices.
  2. Locate underground services (Dial Before You Dig).
  3. Excavate trench (2m deep) using 1.8t excavator.
  4. Install concrete drainage pipe.
  5. Backfill and compact trench.

Hazard Identification and Risk Assessment

Step / TaskPotential HazardWho is at risk?Risk Rating (Before)
Set up traffic controlStruck by public vehicleTraffic controllersH
ExcavationCollapse of trench wallsExcavator operator, ground workerH
ExcavationContact with underground powerAll site personnelH
CompactionVibration (Whole Body)Plant operatorM

Risk Control Measures

Task 1: Establish Traffic Control

Hazard: Struck by vehicle

  • Engineering: Use of approved water-filled barriers and traffic cones per AS 1742.3. Variable Message Sign (VMS) at approach.
  • Administrative: Licensed Traffic Controller implemented. Traffic Management Plan prepared. Traffic controller holds Blue card.
  • PPE: High visibility Class N vest, steel cap boots, safety helmet.

Task 2: Excavation

Hazard: Collapse of trench walls

  • Elimination: Not possible.
  • Engineering: Use of hydraulic trench box (shoring) for depths below 1.5m. Berm or battering where applicable.
  • Administrative: Exclusion zone (1m) maintained. Geotechnical report reviewed. Spotter used for plant movement. No workers in trench while machine is moving.
  • PPE: As above + hard hat with chin strap.

Task 3: Service Locating

Hazard: Contact with underground power

  • Administrative: Plans obtained from Before You Dig Australia. Electronic locating performed by accredited locator. Non-destructive digging (hydro vac) used for potholing to verify depth.
  • PPE: Insulated gloves if working near exposed cables.

Personal Protective Equipment (PPE)

Mandatory:

  • Hi-vis Class N shirt/vest (orange)
  • Safety Helmet (white)
  • Safety Boots (lace up, steel cap)
  • Safety Glasses (clear)

Specific:

  • Hearing protection for compactor operator
  • High visibility rain jacket if wet weather

Emergency Procedures

  • First Aid Kit: Located in site shed / ute.
  • Emergency Contact: Site Supervisor John Smith (0412 345 678).
  • Nearest Hospital: Royal Brisbane Hospital (600m).
  • Gas Strike: Evacate 20m, call 000 and Gas authority.

Training and Competency

All workers hold valid General Construction Induction Cards. Excavator operator holds Verification of Competency. Traffic controllers hold current QLD Traffic Control accreditation.

Sign-Off Section

NameSignatureDateRole
John Smith[Signed]15/10/23Site Supervisor
Mark Jones[Signed]15/10/23Excavator Operator
Sarah Lee[Signed]15/10/23Traffic Controller

Principal Contractor Rep: J. Smith

Notes

Notes:

  • This example is for demonstration only.
  • Risk ratings used a simple matrix (H=High, M=Medium, L=Low).
  • Trench shoring (engineering control) is critical for 2m depth to prevent collapse.

About this Example

Part of the SWMS - Roadworks / Civil Construction document collection

Document Type

SWMS - Roadworks / Civil Construction

Use this SWMS for high-risk roadwork and civil construction tasks including earthmoving, asphalt laying, traffic management, and working near live utilities.

Complexity

complex

Risk Level

high