SAFE WORK METHOD STATEMENT (SWMS)
Company / Project Details
Company Name: [COMPANY NAME] ABN: [ABN] Project Address: [SITE ADDRESS] Date of Preparation: [DATE] Work Activity: General Masonry Work (Bricklaying/Blocklaying/Stonework)
Step 1: Describe the High Risk Construction Work
| High Risk Construction Work Checklist | Yes/No |
|---|---|
| Work involving a risk of a person falling more than 2 metres | [YES/NO] |
| Work carried out on or near pressurised gas distribution mains or piping | [YES/NO] |
| Work carried out on or near chemical, fuel or refrigerant lines | [YES/NO] |
| Work on or near energised electrical installations | [YES/NO] |
| Work involving mobile plant | [YES/NO] |
| Work in or near a confined space | [YES/NO] |
| Work in or near a shaft or trench deeper than 1.5 metres | [YES/NO] |
| Work involving demolition | [YES/NO] |
| Work involving asbestos | [YES/NO] |
| Work in an area that may have a contaminated or flammable atmosphere | [YES/NO] |
| Work involving tilt-up or precast concrete | [YES/NO] |
| Work in an area with movement of powered mobile plant | [YES/NO] |
| Work on a telecommunications tower | [YES/NO] |
| Work near traffic | [YES/NO] |
Description of Work: [Brief description of the specific masonry tasks, e.g., Construction of external brick walls, installation of concrete block retaining walls, laying pavers, mixing mortar.]
Step 2: Hazard Identification
| Step/Task | What is the Hazard? | How could it cause harm? | Risk Rating | Initial Controls |
|---|---|---|---|---|
| 1. Delivery of Materials | Reversing vehicles/mobile plant | Crushing of pedestrians | [H/M/L] | Spotters, exclusion zones, barriers |
| 2. Manual Handling (Unloading bricks/blocks) | Repetitive lifting, heavy loads | Musculoskeletal injury (back/shoulders) | [H/M/L] | Mechanical aids, team lifting, rotation |
| 3. Work at Heights (Scaffolding) / Agresso deck | Fall from height | Serious injury or death | [H/M/L] | Scaff erected by licenced person, edge protection, full planking |
| 4. Mixing Mortar / Cement | Cement dust, skin contact | Dermatitis, respiratory issues | [H/M/L] | PPE (gloves, long sleeves), P2 mask, wash stations |
| 5. Cutting Bricks/Blocks | Silica dust, noise, vibration | Silicosis, hearing loss, HAVS | [H/M/L] | Wet cutting, dust extraction, P2 mask, ear muffs, breaks |
| 6. Falling Objects | Tools, bricks, debris falling | Head injury, fatality | [H/M/L] | Toe boards, tool lanyards, exclusion zones below |
| 7. Using Electrical Tools | Damaged cords, water | Electric shock | [H/M/L] | RCD safety switches, visual inspection, dry area |
| 8. Working Near Traffic/Public | Public interaction, vehicles | Collision | [H/M/L] | Traffic management plan, bollards, signage |
Step 3: Implementation of Control Measures
Hierarchy of Controls applied to key tasks:
1. Working at Heights
- Elimination: Prefabricate walls at ground level where possible.
- Substitution: Use scissor lifts instead of ladders.
- Isolation: Install guardrails (top, mid, toe boards) on scaffolding.
- Engineering: Use scaffold tag system to ensure integrity.
- Administrative: SWMS induction, only work in good weather.
- PPE: Safety helmet, non-slip safety boots.
2. Silica Dust (Cutting)
- Elimination: Order bricks/blocks to exact size to minimise cutting.
- Substitution: Use low silica materials if available.
- Isolation: Cut in designated ventilated area or away from workers.
- Engineering: Use on-tool water suppression or local exhaust ventilation.
- Administrative: Keep area wet, clean up with vacuum (H-class), do not dry sweep.
- PPE: Fit-tested P2 respirator or higher.
3. Manual Handling
- Elimination: Use bulk delivery systems.
- Substitution: Use lighter weight blocks (e.g., Hebel) where structural capacity allows.
- Isolation: Store materials close to work area to reduce travel distance.
- Engineering: Use brick saws, trolleys, pallet jacks, forklifts.
- Administrative: Job rotation, training in safe lifting techniques.
- PPE: Safety boots with good support, gloves.
Step 4: Personal Protective Equipment (PPE)
Minimum PPE Required for all workers:
- High visibility clothing (Class D or N)
- Safety helmet (AS/NZS 1801)
- Safety boots (Steel toe/composite, AS/NZS 2210)
- Protective gloves (Cut resistant or specific for cement)
- Sun protection (Hat, sunscreen, long sleeve shirt)
Task Specific PPE:
- Eye protection (Safety glasses or goggles)
- Hearing protection (Class 5, AS/NZS 1270)
- Respiratory protection (P2/N95 for silica dust)
- Safety use and lanyard (if using travel restraint)
- Disposable overalls (for cutting/cleaning)
Step 5: Emergency Procedures
Incident Reporting: Contact Site Supervisor immediately on [SUPERVISOR PHONE].
First Aid: Location of First Aid Kit: [LOCATION] Location of Eyewash Station: [LOCATION] Nearest Hospital: [HOSPITAL NAME & ADDRESS]
Fire: Contact 000. Location of Fire Extinguishers: [LOCATIONS]. Assembly Point: [ADDRESS].
Step 6: Review and Monitoring
Review Triggers:
- Incident or near miss occurs.
- New equipment or machinery introduced.
- Changes to work environment or scope of works.
- A worker or health and safety representative requests a review.
Review Date: [DATE OR 'Prior to work commencing if scope changes']
Signatures
By signing below, I acknowledge I have read and understood this SWMS and will work in accordance with its controls.
| Name | Role | Signature | Date |
|---|---|---|---|
| Worker Representative | [NAME] | [SIGN] | [DATE] |
| Principal Contractor/PCBU | [NAME] | [SIGN] | [DATE] |
| Worker 1 | [NAME] | [SIGN] | [DATE] |
| Worker 2 | [NAME] | [SIGN] | [DATE] |
| Worker 3 | [NAME] | [SIGN] | [DATE] |
| Worker 4 | [NAME] | [SIGN] | [DATE] |
Keep this SWMS on site at all times while work is being carried out.
About this Template
Part of the SWMS - Masonry Worker (General) document collection
Document Type
SWMS - Masonry Worker (General)
Use this SWMS for general bricklaying, blockwork, and stone masonry tasks on construction sites. It covers high-risk work like working at heights, manual handling, and using powered tools.