SWMS - Retaining Wall Builder Template
Template for SWMS - Retaining Wall Builder. Customize this template for your specific needs.
Professional Review Required
This document involves significant legal, financial, or compliance considerations. You must have a qualified professional review and approve this document before use. Do not rely on this template as legal advice.
Document: SWMS - Retaining Wall Builder
Template Preview
Version 1 • Last updated 7/30/2026
SAFE WORK METHOD STATEMENT (SWMS)
Company / Business Name: [ENTER COMPANY NAME] ABN: [ENTER ABN] Site Address: [ENTER SITE ADDRESS] Date Prepared: [ENTER DATE]
1. JOB DETAILS
Project / Job Name: [ENTER PROJECT NAME] Work Activity: Retaining Wall Construction Start Date: [ENTER START DATE] Finish Date: [ENTER FINISH DATE] Principal Contractor: [ENTER PRINCIPAL CONTRACTOR] SWMS Specific No: [ENTER NUMBER]
2. HIGH RISK CONSTRUCTION WORK (HRCW)
This work is considered HRCW because it involves (check all that apply):
- Risk of a person falling more than 2 metres
- Excavation work deeper than 1.5 metres
- Structural alterations that require support
- Work near overhead powerlines
- Work in or near a confined space
- Use of powered mobile plant
3. TASK BREAKDOWN & HAZARD IDENTIFICATION
| Task / Step | Potential Hazard / Risk | Persons at Risk | Initial Risk Rating (L/M/H) |
|---|---|---|---|
| 1. Site Setup & Underground Service Location | Hitting underground services (gas, electric). Slips/trips on uneven ground. | Workers, Public | H |
| 2. Excavation & Earthworks | Trench collapse / ground failure. Manual handling injuries. Contact with buried objects. | Workers | H |
| 3. Material Handling (Blocks, Sleepers, Gravel) | Strain injuries from lifting. Crush injuries from dropping loads. | Workers | M |
| 4. Base Preparation & Concrete Pouring | Cement burns. Skin irritation. Exposure to silica dust. Noise from equipment. | Workers | M |
| 5. Wall Construction (Installation) | Working at heights (if wall is tall). Falling blocks/materials. Use of power tools (cuts, noise). | Workers | H |
| 6. Backfilling & Compaction | Collapse of wall structure during backfill. Musculoskeletal strain. Noise/Vibration. | Workers | M |
4. RISK ASSESSMENT MATRIX
Consequence: 1 (Minor) to 5 (Fatality) | Likelihood: 1 (Rare) to 5 (Certain)
- Rating H (High): Immediate action required.
- Rating M (Medium): Controls needed.
- Rating L (Low): Monitor.
5. CONTROL MEASURES
| Task / Step | Control Measures (Hierarchy of Controls) | Residual Risk Rating (L/M/H) |
|---|---|---|
| 1. Site Setup & Service Location | Consult: Check Dial Before You Dig plans. Isolate: Identify markers. Admin: Tool box talk to review plans. PPE: Safety boots, high viz. | M |
| 2. Excavation & Earthworks | Engineer: Use battering or trench shields for trenches >1.5m. Admin: Keep workers away from excavator swing radius. Admin: Exclusion zone for machinery. PPE: Safety boots, high viz, gloves. | L |
| 3. Material Handling | Substitute: Use mechanical aids (crane, bobcat, dingo) for heavy loads. Admin: Team lifting technique for manual loads. Admin: Rotate tasks to avoid fatigue. PPE: Gloves, safety boots. | M |
| 4. Base Preparation & Concrete | Substitute: Use pre-mixed concrete. Engineer: Use wet cutting methods to control dust. PPE: Gloves, long sleeves, goggles, dust mask, hearing protection. | L |
| 5. Wall Construction | Substitute: Use blocks with handles for grip. Admin: Ensure stable footing. Admin: Do not stack blocks too high. PPE: Safety glasses, gloves, dust mask. | L |
| 6. Backfilling | Engineer: Compact in layers as per engineer specs. Admin: Ensure drainage is installed correctly. Admin: Visual inspection of wall integrity. | L |
6. PERSONAL PROTECTIVE EQUIPMENT (PPE)
Mandatory for all workers:
- Safety Helmet (Class 1 or 2)
- High Visibility Clothing
- Safety Boots (Steel capped)
- Sun Protection (Hat, sunscreen, long sleeves)
Task Specific:
- Eye Protection (Safety glasses/goggles)
- Hearing Protection (Ear muffs/plugs)
- Dust Mask (P2/N95)
- Gloves (Rubber/Leather)
- Wet Weather Gear
7. EMERGENCY PROCEDURES
- First Aid: Location of First Aid Kit: [ENTER LOCATION] | First Aid Officer: [ENTER NAME]
- Emergency Services: 000
- Hospital: Nearest hospital is [ENTER HOSPITAL]
- Emergency Assembly Point: [ENTER LOCATION]
- Fire: Extinguishers located at [ENTER LOCATION]
- Incident Reporting: Report all incidents to [ENTER SUPERVISOR NAME] immediately.
8. TRAINING & COMPETENCY
- All workers must receive a site induction.
- High Risk Work Licences held: [ENTER LICENSE NUMBERS]
- Plant operator tickets held: [ENTER TICKET NUMBERS]
9. SIGN OFF
I have read and understood this SWMS and agree to follow the control measures.
| Worker Name | Signature | Date |
|---|---|---|
| [ENTER NAME] | [SIGN] | [DATE] |
| [ENTER NAME] | [SIGN] | [DATE] |
| [ENTER NAME] | [SIGN] | [DATE] |
| [ENTER NAME] | [SIGN] | [DATE] |
Principal Contractor / PCBU Representative: Name: [ENTER NAME] Signature: [SIGN] Date: [DATE]
About this Template
Part of the SWMS - Retaining Wall Builder document collection
Document Type
SWMS - Retaining Wall Builder
This SWMS is required for any retaining wall construction involving excavation deeper than 1.5 metres or work near overhead powerlines. It covers the specific risks of earthworks, heavy lifting, and concrete handling.