Safe Work Method Statement (SWMS)
Company Details
Company Name: [COMPANY NAME] ABN: [ABN] Address: [ADDRESS]
Project / Job Details
Project Name: [PROJECT NAME] Job Number: [JOB NUMBER] Site Address: [SITE ADDRESS] Date of Issue: [DATE]
High Risk Construction Work (HRCW)
This SWMS applies to the following High Risk Construction Work (Check all that apply):
- Work that involves a risk of a person falling more than 2 metres
- Excavation work (including trenching) deeper than 1.5 metres
- Work in or near a confined space
- Work in or near a shaft or trench deeper than 1.5 metres
- Work on or near pressurised gas distribution mains or piping
- Work on or near chemical, fuel or refrigerant lines
- Work on or near energised electrical installations or services
- Work in an area that may have a contaminated or flammable atmosphere
- Work near traffic, mobile plant (e.g. roadworks)
- Work near or on water
- Work involving demolition
- Work involving structural alterations
- Work involving the use of explosives
- Work on or adjacent to railway lines
- Work in an area at a workplace in which there is movement of powered mobile plant
Description of Tasks
[List the specific tasks to be performed, e.g., Installation of traffic management devices, Excavation of trench for drainage, Placement of road base, Compaction of asphalt]
Hazard Identification and Risk Assessment
| Step / Task | Potential Hazard | Who is at Risk? | Risk Rating (Before Controls) | H | M | L |
|---|---|---|---|---|---|---|
| [e.g., Setting up traffic control] | [e.g., Struck by vehicle] | [e.g., Traffic controllers, public] | [H/M/L] | |||
| [e.g., Excavation] | [e.g., Ground collapse] | [e.g., Plant operator, ground workers] | [H/M/L] | |||
| [e.g., Operating roller] | [e.g., Rollover, noise] | [e.g., Operator] | [H/M/L] | |||
| [e.g., Breaking concrete] | [e.g., Dust, silica, vibration] | [e.g., Labourer] | [H/M/L] | |||
| [e.g., Service locating] | [e.g., Strike cable / pipe] | [e.g., Locator] | [H/M/L] |
Risk Control Measures
For each task listed above, implement controls using the Hierarchy of Controls.
Task 1: [TASK NAME]
Hazard: [HAZARD]
- Elimination: [Can the hazard be removed?]
- Substitution: [Can something less hazardous be used?]
- Engineering: [e.g., Use of concrete barriers, signage, trench shoring]
- Administrative: [e.g., SWMS briefing, spotters, exclusion zones, permit systems, rotate workers]
- PPE: [List PPE required]
Task 2: [TASK NAME]
Hazard: [HAZARD]
- Elimination: [Can the hazard be removed?]
- Substitution: [Can something less hazardous be used?]
- Engineering: [e.g., Machine guards, ROPS, dust extraction]
- Administrative: [e.g., Traffic management plan, pre-start checks]
- PPE: [List PPE required]
(Repeat for all tasks)
Personal Protective Equipment (PPE)
Mandatory PPE for all workers:
- High visibility clothing (Class D or N)
- Safety Helmet (AS/NZS 1801)
- Safety Boots (AS/NZS 2210.3)
- Safety glasses or goggles
Task Specific PPE:
- Hearing protection (Class 5)
- Gloves
- Respiratory protection (P2 or higher)
- High visibility vest with sleeves
- Sun protection
Emergency Procedures
- Location of First Aid Kit: [LOCATION]
- Location of Fire Extinguisher: [LOCATION]
- Nearest Hospital: [NAME AND ADDRESS]
- Emergency Contact Person: [NAME] - [PHONE NUMBER]
- Emergency Services Dial: 000
- Evacuation Assembly Point: [LOCATION]
Specific Emergency Instructions:
- For injuries: Stop work, administer first aid, call 000.
- For service strikes: Stop work immediately, clear area, call service authority.
- For traffic incidents: Secure scene, divert traffic if safe, call police.
Training and Competency
We confirm that all workers listed in the sign-off section have received the necessary training and instruction to perform the work safely.
- General Construction Induction (White Card)
- Traffic Controller Accreditation
- High Risk Work Licence (e.g., Dogman, Forklift)
- Confined Space Entry Training
- Plant Operator Verification of Competency
Review and Revision
This SWMS will be reviewed:
- Before work commences
- If there is a change in work procedures
- If a new hazard is identified
- If a notifiable incident occurs
- On a regular basis (every [X] months)
Sign-Off Section
Worker Acknowledgement: I have read and understood the contents of this SWMS. I agree to follow all control measures and use the PPE provided.
| Name | Signature | Date | Trade / Role |
|---|---|---|---|
| [Name] | [Sign] | [Date] | [Role] |
| [Name] | [Sign] | [Date] | [Role] |
| [Name] | [Sign] | [Date] | [Role] |
Principal Contractor / PCBU Representative: I confirm this SWMS adequately addresses the risks associated with this work.
Name: __________________ Signature: __________________ Date: ________________
About this Template
Part of the SWMS - Roadworks / Civil Construction document collection
Document Type
SWMS - Roadworks / Civil Construction
Use this SWMS for high-risk roadwork and civil construction tasks including earthmoving, asphalt laying, traffic management, and working near live utilities.